A punch list is the last list on a job. Everything on it is small on its own: a chipped tile, a door that rubs, paint on a socket faceplate, a tap that drips. Together they decide whether the handover goes well, and a vague list is how the same item gets fixed twice or not at all. The British call it a snag list, Americans a punch list, and a lot of contracts simply say defect list. The method is the same under every name.
This guide covers the walkthrough itself: what to prepare, the order to walk in, what to write for each item, how to photograph and mark it up, how to split the list by trade, and how to close it out.
Before the walk
Preparation decides how long the walk takes.
- Get the plans. A floor plan for each level, with room names or numbers that everyone uses. If the drawings use “Bed 2” and the site uses “back bedroom”, pick one and write it on the plan before you start.
- Agree what counts as an item. A punch item is work that was in scope and is not finished or not right. A request for something new is a change, and it goes on a different list with a price. Saying this before the walk saves an argument during it.
- Do your own pass first. If you are the contractor, walk the job yourself or send the site manager a few days before the client walkthrough. Every item you find and fix first is one the client never sees.
- Agree who attends. The person who will sign the list should be there, plus whoever has to accept the work for the builder. A list written by one side and sent to the other gets disputed line by line.
- Pack for it. A charged phone or tablet, a torch, a spirit level, a tape measure, low-tack tape to mark spots, and a socket tester.
Walk in a fixed order
Pick a route and use the same one in every room. A common one is clockwise from the door, and top to bottom in each part of the room:
- Ceiling: cracks, paint finish, light fittings, smoke detectors, access hatches.
- Walls: plaster finish, paint runs and misses, sealant lines, tiling and grout, damage from other trades.
- Openings: doors that latch, close without rubbing and have their stops and ironmongery; windows that open, lock and seal; sills and reveals.
- Floor: finish, thresholds, gaps at skirting, damage under protection that was just lifted.
- Fixtures and services: run every tap, flush every toilet, try every switch and socket, open every cupboard and drawer, run the heating and extraction.
Services only show up when you use them, so test them. Then step back at the door and take one wide photo of the room as a record of how it looked on the day.
What to record for each item
Write each item so that a tradesperson who was not on the walk can find it, fix it and know when it is finished. That needs the same fields every time:
| Field | What goes in it | Example |
|---|---|---|
| Number | One series for the whole job, never reused | 047 |
| Location | Level, room, and where in the room | Level 2, Kitchen, left of the window |
| Description | What is wrong, and what finished looks like | Silicone missing along worktop upstand; run a continuous bead |
| Photo | A wide shot for context and a close-up of the defect | Two photos, marked up |
| Trade | The one trade that fixes it | Decorating |
| Priority | How much it matters to handover | High |
| Assigned to | The company or person, by name | Smith Decorators |
| Due | A date | Friday 28 November |
| Status | Where it is in the workflow | Open |
The description is where most lists fail. “Paint” tells the decorator nothing. “Paint missing on the head of the door frame, bathroom side” tells them where to stand. Write the defect and the location in one line, and add the expected result when it is not obvious.
Keep one running number series for the whole project, with the location in its own field. When an item turns out to be nothing, mark it as not an issue instead of deleting it, so the numbers stay continuous and nobody wonders what happened to 048.
Photograph it so it can be found
A close-up of a scratch could be anywhere in the building. Take two photos per item:
- A context shot from a few steps back, so the photo shows which wall, which door, which unit.
- A close-up of the defect itself, with something for scale where size matters.
Then mark the photo up. An arrow or a circle on the exact spot, a short label, a dimension line where a gap or a level is the problem. If people, number plates or someone’s paperwork are in the frame, blur them before the photo leaves your device. Keep the original photo unmarked as well; if a fix is disputed later, the untouched image with its date and time is the one that counts.
Pin each item on the floor plan too. A pin per item turns the plan into a map of the job, and a trade can walk straight to its items instead of reading room names.
Split the list by trade
The client sees one list. The trades each need their own. Give every item exactly one trade, and when one defect needs two (an electrician to move a socket, then a decorator to make good), log it as two items. The usual trade split on a fit-out looks like this:
- General / main contractor
- Plastering and drylining
- Joinery (doors, skirting, architraves, cupboards)
- Decorating
- Electrical
- Plumbing and heating
- Flooring and tiling
- Glazing
- Roofing and external works
- Fire safety
- Cleaning
Send each contractor only their items, with the photos and plan pins, as a task sheet they can work from. A plumber does not need to scroll past forty paint touch-ups to find the two leaks.
Track every item to closed
Count an item as done only after someone has checked the fix on site. A status set that records both steps:
| Status | Meaning |
|---|---|
| Open | Recorded, nothing done yet |
| In progress | The trade has started |
| Fixed | The trade says it is done |
| Verified | The inspector or site manager has checked it on site |
| Closed | Accepted and off the list |
| Not an issue | Looked at and found to be acceptable, kept for the record |
For the back-check, take an after photo from the same spot as the before photo. Side by side in the report, the pair shows the fix more clearly than any description, and it answers the question “was this ever done?” months later.
Sign-off and handover
Walk the client or their representative through the list item by item, on site if you can, and record their answer for each: accepted or not accepted, with a comment where they disagree. Then both sides sign the same version of the list. If anything changes afterwards, issue a new revision with its own letter or number instead of editing the signed one.
What a signature at handover means in law depends on your contract and your country, and some forms of contract define the handover inspection in detail. Read the contract, and take advice where the money is significant. The list itself should still be the same: numbered, located, photographed, assigned and signed.
A punch list template you can copy
If you are working in a spreadsheet, these columns cover the fields above. Paste them as the header row:
Number, Location, Description, Trade, Priority, Assigned to, Due, Status, Photo files, Date found, Date closed
Name the photo files after the item, for example 047_Kitchen_Open_1.jpg, and keep them in one folder with the sheet. The weak point is the photos: they live in a folder, not in the row, and nothing ties a marked-up photo to a plan location.
For a remedial job you will price separately, the client usually needs an estimate before the work starts. How to write an estimate covers what goes on one.
Doing this in Sitewalk
Sitewalk is built for this walk. You import the plan as a PDF or an image, or, on an iPhone Pro or iPad Pro with a LiDAR Scanner, scan a room into a floor plan. Then you photograph each defect. The issue is numbered, time-stamped and pinned on the plan where you put it, and the pin takes the colour of its status.
Photo markup has arrows, circles, rectangles, revision clouds, freehand, text, numbered markers, a highlighter, dimension lines and blur. The markup is stored separately and the original photo is never changed, and each photo keeps its time, location and a SHA-256 fingerprint of the original file. Each issue takes a title, description, area, trade (from a list of 14), priority from Low to Critical, assignee, due date, cost and tags. Wording you use often goes into a comment library for the next job. You can also describe an issue by voice; where the device supports it, speech is transcribed on the device.
The statuses are the six in the table above, with the same colour and word on the pin, in the list and in the PDF. An after photo sits beside the before photo in the report. The app can call items snags, punch items or defects, so the report reads as a snagging report, a punch list report or a defect report.
At handover you can walk the client through each item on the device, marking it accepted or not accepted, and both of you sign there; signatures belong to that revision of the report only. The report comes in four designs (Professional, Visual, Compact Table and Classic) on A4 or US Letter, grouped by area, trade, status or assignee, with your logo and report number. Exports are a PDF, a CSV that opens in Excel and Numbers, a ZIP of the photos named like the example above, and one task sheet per assignee. Handover, inspection and safety-walk checklists are included, and a failed checklist item becomes a linked issue.
There is no account and no server. Projects, photos and reports stay on the device and work without a connection, which matters in basements and new builds with no signal. Sitewalk runs on iPhone and iPad, and the interface is in English. The free version holds one active project, 30 issues per project and one plan, with Professional reports that carry a small Sitewalk footer. Sitewalk Pro, monthly, yearly or as a one-time purchase, removes the limits and the footer and adds the other designs, LiDAR plans, voice-to-issue, before and after photos, signatures and walk-through, the site diary, and the CSV, photo ZIP and task sheet exports.